Manufacturing plant feasibility: start from the bill of materials

A manufacturing plant feasibility study lenders trust starts with the bill of materials and line capacity, then capital cost, ramp-up and debt.

By Roman Cintula · · 4 min read

Industrial factory interior

Most first drafts of a factory business plan start with a revenue forecast and a single number for capital cost. Lenders and investors read a plant the other way round. They ask what goes into each unit, how many units the machines can physically make, what the plant costs line by line, and whether cash flow covers the loan while the plant is still filling up. A manufacturing plant feasibility study built in that order is harder to write and much harder to pick apart. This article goes through the steps.

Cost each product from its bill of materials

Start with the product. A bill of materials lists every raw material and purchased component in one unit, with quantities. Price each line, add an allowance for scrap and any import duty, and you have the material cost per unit. Add direct labour and the energy used per unit, and you have the variable cost. The difference between that and the selling price is the contribution each unit makes toward fixed costs and profit.

Doing this for every product shows which ones carry the plant and which ones lose money once their real material use is counted. It also sets up the most important sensitivity in most plants, which is what happens when a raw material price moves. Whether your customer contracts let you pass a cost increase through, fully, partly or not at all, belongs in the model as an explicit assumption.

Test demand against line capacity

A sales forecast means nothing if the plant cannot make the volume. Each production line has a number of machines, shifts, hours per shift, operating days and a planned uptime after maintenance and changeovers. Together those give the machine-hours available in a year. Each product needs a certain amount of time on a line, so the sales plan converts into machine-hours required.

Comparing the two, year by year, shows when a line runs out of capacity. At that point the choices are to add a shift, add a machine or sell less, and each has a cost. A model that lets sales grow past what the lines can produce is one of the first things an experienced reviewer will find.

Itemize the capital cost

The equipment quote is one part of the cost of a plant. A full budget also carries land and site works, the building, plant utilities such as power supply, compressed air and cooling, installation, freight and duty, spare parts, vehicles, information technology, engineering and a contingency. Then come the costs of getting ready to operate: hiring and training staff before production starts, and commissioning.

Having built a pyrolysis plant in Alberta, I would treat the gap between a vendor’s equipment price and the installed cost as the most common source of overruns in any plant budget. The drivers are covered in pyrolysis plant capital cost and what drives it, and most apply to any process plant.

Construction, ramp-up and working capital

Spending during construction does not arrive evenly. It usually starts slowly, peaks in the middle and tails off, and the funding has to match it month by month. Lenders generally want equity spent first or alongside debt, and interest accrues on the loan before the plant earns anything. That interest is part of the project cost.

Once production starts, a new plant takes time to reach its planned output and quality. During ramp-up, fixed costs are at full level while sales are not. Working capital builds at the same time: raw materials and finished goods sit in inventory, and customers pay weeks after delivery. Many plants that are profitable on paper run short of cash in the first two years for these reasons. Annual figures can hide the low point, so the early operating period is worth modelling by month.

Operating costs and tax

Direct labour moves with production, though not perfectly, because a core crew is needed even at low volumes. Plant overhead (supervision, maintenance, quality), energy, insurance, property tax and administrative staff are largely fixed. Separating fixed from variable costs is what allows a break-even calculation: the level of sales, or of utilization, at which the plant covers all its costs.

Tax rules for manufacturing differ by country and often include accelerated depreciation, investment tax credits, grants or tax holidays. These can change the return materially and should be modelled from the actual rules for the location, with advice.

What lenders test

A lender will size the loan to the plant’s cash flow using a debt service coverage ratio, test the weakest year of the ramp-up, and often require a reserve account and limits on distributions. Equipment is sometimes financed separately from the main loan, and a working capital facility covers inventory and receivables. The tests are described in what a lender-ready financial model looks like.

A worked template

Launchwright’s manufacturing plant model follows this order: products and bill of materials, line capacity, staffing by role, a 14-line capital budget, monthly construction funding, driver-based operating costs, tax and returns, with presets for the United States, Canada and a generic international case. Its default case is an illustrative plastics packaging plant in Ohio with four products on three lines, 91 staff and a project cost of about $33.5 million. On those template assumptions the Due Diligence Edition shows an equity internal rate of return (IRR) of 17.3%, a minimum debt service coverage ratio of 1.76 times in repayment years and break-even at 57% of forecast revenue in operating year five. Prices, material costs and equipment costs in the default case are template assumptions, to be replaced with quotes for your own project.

Testing whether a plant is worth building, before money is spent on engineering, is part of our strategy and project development work.

This article is general information, not investment, tax or engineering advice.